BEL and Kuvempu circle underpass
UPCOMING EVENTS
BEL and Kuvempu circle underpass
Project number | 13683 |
Opened by | USN Admin |
Opened On | 2020-08-18 14:11:00 +0530 |
Operations | View all project cases |
BEL and Kuvempu circle underpass - details as on 30.12.2011 Sl.No. Items Project Details 1 Project Name Construction of underpadd along ORR at BEL and Kuvempu circles Owner Name BANGALORE DEVELOPMENT AUTHORITY 3 Financing KUIDFC 4 Architect/Consultant M/s. MANASA CONSULTANTS, Malleswaram, Bangalore 5 Contractor M/s. PJB CONSTRUCTIONS 6 Project start date 09/09/2010 7 Project duration 15 months 8 Project cost Rs.39.93 Crores 9 Amount released till date Rs.12.76 Crores 10 Sub-contractor details (If any) Nil 11 Percentage of work completion 40%