Devarabeesanahalli Flyover
UPCOMING EVENTS
Devarabeesanahalli Flyover
Project number | 13665 |
Opened by | USN Admin |
Opened On | 2020-08-18 14:08:31 +0530 |
Operations | View all project cases |
Devarabeesanahalli Flyover- details as on 17.12.2011 Sl.No. Items Project Details 1 Project Name Construction of Grade Separator at HSR 14th main, Bellandur and Devarabeesanahalli (Pkg-1) along ORR 2 Owner Name BANGALORE DEVELOPMENT AUTHORITY 3 Financing KUIDFC 4 Architect/Consultant M/s. STUP CONSULTANTS PVT. LTD., 5 Contractor M/s. SIMPLEX INFRASTRUCTURE LIMITED 6 Project start date 09/09/2009 7 Project duration 15 months (extended upto 22/12/2011) 8 Project cost Rs.40.82 Crores 9 Amount released till date Rs.17.20 Crores 10 Sub-contractor details (If any) Nil 11 Percentage of work completion 55%