HOT TOPICS
SPOTLIGHT AGENCIES
Work is on, June 2010 new date
silkboard - 22 March, 2010 | Bangalore | Whitefield | Transportation | Infrastructure | Flyovers and underpasses | Kadugodi
Work is on, many have confirmed. June 2010 is being comunicated as the planned end date for remaining work. Residents or commuters of the area should post pictures here to keep tab on the work, so that all get to know if June 2010 date is realistic.
Given all the new information, there is no need for planning a protest right now, let us wait till end of May. Sounds good?
COMMENTS
Work is on, June 2010 new date | Photos
janiannapurna - 25 March, 2010 - 09:32
Thanks Surya for the snaps.Looks like something is really happening there.Let's hope for the best
Work is on, June 2010 new date
suryakamal - 22 March, 2010 - 09:54
Hi,
Yes, for sure work is in progress.
Apart from the work next to police station, over the past week, two iron girders (more like scaffoldings) have come up between the tracks (cant figure out whether they are some kind of support for erection work or will they stay there for ever!).
I haven't had chance to take photographs; but, will try to share in the next couple of days!
Cheers.....Surya
Work is on, June 2010 new date | Photos
suryakamal - 23 March, 2010 - 15:34
Hi,
Here are some snaps (not good quality) taken this evening on my mobile! Hope to do a better job - may be over this weekend.
http://picasaweb.google.co.in/suryakamal/Bridge22ndMarch2010#
Cheers...Surya
Thanks for the pictures Surya
silkboard - 25 March, 2010 - 09:55
Will be fun to record the critical part of work - putting that long span over the temporary support structures. Should ask them when they plan to do it. I am sure it will be done in the night. We can go record with our night cams!
Latest update about Kadugodi ROB
suryakamal - 26 March, 2010 - 06:26
Hi,
Here is a mail in circulation in Chaitanya group.... I haven't physically checked; but, looks like a good update :)
Over the weekend, will try to take some snaps and share!
Cheers...Surya
The wait is almost over – after years of staring at the ramps of the ROB that went nowhere – we're happy to report that the first piece of steel girder over the rail lines was put in place at 1:30 AM on 26-March-2010.
The work started just past midnight after the electric lines were disconnected from mains over most of the tracks. 2 tracks on the ashram side were still operational. A Huge crane was brought in and locked in place at around 12:30 AM. The crane did a dry run – turning a full 360 degrees with its lifting arm fully extended to ensure that it did not damage any electric lines. A big truck brought the first piece of the steel girder ( 16 mts long ) along the crane and then the actual work started. The huge steel girder was hoisted up, turned, expertly guided between the electric lines and placed safely in its designated place. The entire operation was beautifully orchestrated by a crew of around 50 people from railways and the contractor. I know it sounds a bit simple but considering he weight that the crane was carrying and the narrow distance between the electric lines – this thing should be on Discovery Channel.
The site engineer shared some information with us – here a brief of what we learned :
- There will be 2 steel girders laid over the railway tracks. Each girder will be 42 meters (m ) long.
- Each girder will have 3 pieces, 2 pieces of 16 m each ( these start from the end of the ramps ) and a middle piece of 10 m.
- The plan is to put the first 16 m piece ( kadugodi side ) and the middle ( 10 m ) piece in place today.
- Tomorrow night they will put the 3rd 16 m piece ( ashram side ) in place.
- Once all 3 pieces are in place they will be welded and riveted together.
- Once this monolith is ready, it will be shifted by a few meters ( parallel to it's current position ) , so that the temporary support structure can be used to assemble the 2nd girder.
- Once both the long 42m girders are in place – they will be cross connected with more steel and a steel sheet will be laid over them and that will form the base of the eventual road.
We also learned from people at the site that there might not be any weight limit on the ROB – meaning that school buses may be able to go over the bridge.
Latest update about Kadugodi ROB 28th March
suryakamal - 30 March, 2010 - 11:30
Hi,
Couple of snaps - just to share the progress. These were taken on Sat morning.
Though, didn't see any activity on Sunday - overall seems to be progressing well.
http://picasaweb.google.co.in/suryakamal/Bridge280310#
Cheers....Surya
Work in full swing?
silkboard - 30 March, 2010 - 17:38
I hear that the level crossing has been close for a few days. The crossing may or may not open tomorrow (was supposed to shut only for a week), but there is a chance that the bridge may be ready by May itself, few weeks ahead of June 1 deadline (which is not really an official one).
Subbu and Sudipto talk some detail on this citizenmatters article (from Subbu himself)
Subbu:
I spoke to Kumar, MD of KPR/Balaji. He says they have asked for 6-days of closure to launch the girder which will start tomorrow midnight.
In reality he says morning traffic will be blocked for the first two days of the 6-days and after that for peak hours they will open the line.
During blockage, the Channasandra Road<-->Hope Farm is the alternative route.
Sudipto:
Subbu,
I walked up to the shed last night and talked to one of the supervisors. Wanted to know how long the level crossing would be closed. I got a different and interesting story. He said that the LC is closed for good. The commute in that route will only start once the bridge is really complete. He added that there will be footbridge connecting the bustand to the other side and that the platforms of whitefield station will be extended to the point where the LC is there right now.
The Bridge in his estimate is May end/June for deployment.
I think I would go there myself tomorrow evening to get some details from the workers.
Kadugodi ROB will be insufficient
Naveen - 31 March, 2010 - 07:16
There have been comments about the ROB - if it really will be sufficient in width. Roads at both ends of the bridge are much wider than the bridge & very large number of apt complexes have been springing up on the other side of the bridge (Sai Baba ashram side).
Unless Metro is extended upto Kadugodi (adjacent Whitefield SWR station & Bus terminus), the bridge will become a bottle neck soon since it will have only two lanes. Also, the manned level crossing will be permanently closed once the bridge has been completed (similar to Lingarajpuram, Banaswadi rd, etc). Thus, two lanes will have to cater to all traffic.
I think railways need to start planning another bridge (adjacent the existing one) to provide for increased capacity soonest.
Latest update about Kadugodi ROB 8th April
suryakamal - 8 April, 2010 - 04:37
Hi,
Noticed last night, the welded / riveted girder is now moved into its final place (!) from the scaffolding. Now the scaffolding is ready to take last girder...
Cheers...Surya
Relocation of Kadugodi Bus Stand
magarwal10 - 19 April, 2010 - 09:33
Now it is expected that Railway Overbridge at Kadugodi will be completed soon. It is the time to think about extension of Volvo bus service at least upto Safal Market as lot of residential layout are upcoming in this stretch. Kadugodi bus stand can be relocated somewhere near Safal Market where the land prices are definitely cheaper as compared to the existing location of bus stand.
If the service is extended beyond Kadugodi Depot / Stand It would be beneficial for the resident who will use the buses more which will also generate more revenue for BMTC.
An email has been sent to BMTC on 16.04.2010 in this regard.
Here is June!
suryakamal - 31 May, 2010 - 19:40
Here is June 2010 and where is the ROB? I have not been in town for the past couple of weeks and anyone living around know the status?
Regards...Surya
Missed their date?
silkboard - 3 June, 2010 - 08:09
Doesn't look like the bridge will be ready in June. But work is definitely on, movement seems slow, but might be for technical reasons.
BTW, The complaint I had filed on DPAR website has generated lots of responses from government departments.
- First I got a letter from DPAR itself saying that they will fwd the grievance to railways.
- Then I got a letter from railways saying they will forward to BBMP.
- Then, I got another letter from BBMP which sort of says they will send details of work status once they get it (from SW railways?).
So basically, 3 months after filing a grievance at DPAR website, I am impressed with the grievance process - so many letters to engage the complainant. But no real information, or promises in any of them.
ROB near to complete- Putting Tar
sridhar75 - 2 July, 2010 - 08:51
Good news is they started putting Tar so we can expect completion of this ROB with in two weeks time.
Thanks,
Sridhar Challa.
ROB Inauguration date ?!
suryakamal - 2 July, 2010 - 10:38
Hi,
Have been hearing about 8th July 2010 (yes, the year is correct) as the Inauguration date for the Kadugodi ROB.
Anyone knows, if this true?? I have also heard lots of buzz about ongoing road work, etc.
Cheers....Surya
Hi Surya, They already put
sridhar75 - 2 July, 2010 - 13:24
Hi Surya,
They already put Tar on one side of the bridge (Hopefarm side), may be during the weekend they might put Tar on other part (Ashram Side). Any left over work like Painting, cleaning work can be done in 3 days. So I think 8th of July is reasonable date for the Inauguration.
Any other members have any other updates on this?
BTW, I am just wondering how they are going to erect electric poles. I don't see any provision for erecting the electric poles.
Anyone has any idea about this?
Thanks,
Sridhar Challa.
Photos in the other thread...
suryakamal - 3 July, 2010 - 02:04
Hi Sridhar,
Yes, you are right. I posted another update and photos (taken last evening) on the other thread.....http://praja.in/en/projects/2869/announcement/kadugodi-flyover-almost-ready#comment-22773
Regards....Surya
Today (15/07/2010) ROB is not inaugurated, but Vehicles are movi
sridhar75 - 15 July, 2010 - 13:22
Hi,
Today (15/07/2010) ROB is not inaugurated, however vehicles (like two wheelers, Autos, Cars and Sumos) are moving on this ROB.
I am not sure how safe it is travel on this ROB before inauguration.
Thanks,
Sridhar Challa.
bridge is safe?!
sanjayv - 15 July, 2010 - 16:38
According to this thread on citizen matters (read through the comments), the Chief Engineer of the Railways declared it safe. It is pending some kind of communication process between the Railways, BBMP and the traffic police to be formally opened.
Look for comments by Subramaniam Vincent, the editor of Citizen Matters who followed this matter relentlessly.
Thank you for the info
sridhar75 - 16 July, 2010 - 11:43
Thank you Sanjay for the inoformation.
PRAJA.IN COMMENT GUIDELINES
Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!