Posts : BMRCL

BMRC Ph-2 Tracking

Sanjeev - 18-NOV-2014

Majority of Construction contracts Tenders were suppose to be published during Q2/ Q3 and Q4  of 2013-14  and  balance works contract tenders to be called during  Q1/ Q2 / Q3 / Q4 of 2014-15

Alos Road widening and Road Streangthening ,  Demolution of properties Tenders were to be called during Q3/Q4  of 2013 -14

Before Phase 1 Metro Go Live - Lot could be done

Vasanth - 7-SEP-2014

Government of Karnataka planned for Bangalore Metro 11 years back, way back in 2003 and the actual work started only in late 2007. Bangaloreans could get first ride of Meto in late 2011, after 4 years of start of project for only 7kms. Second stretch of Reach 3 covering 11kms was opened after 2.5 years in March 2014. 

Metro to ITPL

srinidhi - 8-AUG-2014

Sanjeev brought out a very valid point on how access to ITPL/whitefield is going to get affected in the next coming years because of the metro construction there.

It is beyond doubt that we need the metro going there and soon..it should have happened years ago as part of phase I itself..but it will be happening now..

Metro ph 2 and Jayadeva interchange

srinidhi - 12-MAY-2014

It was in 2010, in a meeting for tendersure plan review at STUP office that a discussion on marenahalli road came up and the review board member said that STUP had proposed a elevated road and metro line resting on the same pillar was the best sollution on marenahalli road to handle traffic on the busy jayanagar/btm stretch including Jayadeva.

Incremental Metro Extension in Phase 2

Vasanth - 22-APR-2014

Metro Phase 2 works are going to start very soon. But how long it would take? Phase 1 which started in 2007, saw the light in 2011 partially. For complete Phase 1 to complete, it would be end of 2015 or even 2016. Almost close to 9 years. Phase 2 in the phase 1 pace might take another 9 years. If the work starts now in June / July, it might complete somwhere in 2023.

Can the Metro depend on government-run BESCOM?

murali772 - 7-APR-2014

Metro services on the recently inaugurated Peenya section were disrupted for over an hour on Sunday afternoon following a power failure.

City debt stands at 14K crores!

srinidhi - 17-DEC-2013

The city's civic agencies thrive on borrowing.Outstanding

Do We Need Bommasandra Line of Metro Starting from Jayanagar

Vasanth - 29-AUG-2013

With the recent announcement of Elevated Road from Jayadeva to Silkboard via BTM, which is the main bottleneck on the Outer Ring Road, I was thinking is the Metro investment worth here.

Halt massive Bangalore Metro investments, give satellite town connectivity its due first

silkboard - 19-AUG-2013

Have been reading up on Metro's Phase 2A and Phase 3 plans and few thoughts cross my mind.

How is Metro Ph II best done?

srinidhi - 15-AUG-2013

Metro ph II is ready to kick off soon with the approvals coming in from Delhi. There is still lot of discussions pending on the utility and the routes. With the change in ledership there is a possible  opportunity to start discussions to optimize routes. The current PH II route with stations is in the below link: