ssheragu - 10-APR-2008
i have small suggestions the bus tickets issuedby BMTC may be in multiples of Rs 5 or Rs 10 but not odd figures like Rs6, Rs 13 , Rs 14 etc as this will cretae problem of change Srinath Heragu |
Part III: South East CBD areas not connected Naveen - 10-APR-2008
South East
CBD areas not connected.
The attached Sketch “CTTP–No MRTS
within SE CBD” indicates that the very large area marked by a red
outline – the South-Eastern quadrant of the inner core area within CRR
that has important CBD points such as JC Rd (105,000 PCUs), KH Rd
(96,000 PCUs), Lalbagh Rd (61,000 PCUs), Corporation /Hudson Circle
& Richmond Circle does not have convenient Mass transit within easy
reach. Very large nos. of commuters travel to activity centers around
these areas daily & school going children /staff to various schools
& offices arriving by private vehicles choke up Richmond /Residency
roads during school times. The only TTMC at Shantinagar may not attract
these commuters due to the inconvenience of long distances, transfer to
buses & the time delay involved.
|
Naveen - 10-APR-2008
Commuter
Rail Services (CRS)
There has been frequent &
repeated mention of CRS on existing rail tracks in several previous
study reports (since 1981), but with no follow up action so far. The
CTTP-2007 report has recommended an increase in the CRS network to
204km in three phases. It is not clear if this is being seriously
pursued with the Railways. Some land acquisition is also involved,
& there are many questions as to which body will build &
operate the CRS network, & also the type of rolling stock &
service /quality levels, ticket pricing, etc.
|
Part I: Airport Rail Link - The Monorail Option Naveen - 10-APR-2008
Airport
Rail Link – the Monorail Option
The Airport-City rail link has been a
much visited topic, but nothing seems to have been finalized, so far.
The central government had recognized mass transit systems as vital for
larger cities’ needs & had previously offered assistance to the
tune of 30% (similar to Metro-rail systems), which is a small
contribution – 70% still has to be met by state government & BIAL,
including loans & debts. Negotiations always seem to have ended in
deadlock as agreements over revenue sharing are uncertain with changing
stands by the government/s involved. It appears that the central
government has now changed its stand & is willing to provide more
participation as this is a vital sector that can have far reaching
consequences for the country’s economy.
|
Naveen - 10-APR-2008
Monorail
About 60 kms of Monorail /Light rail has been recommended in the CTTP report on various potentially high-growth corridors (Western portion of ORR & Bannerghatta road) in the CTTP report. |
Traffic/Transport Issues & CTTP-2007 Naveen - 10-APR-2008
There is deep concern about unmanageable volumes of traffic, the deteriorating road discipline & difficulties in commuting, all calling for very urgent interventions. |
Traffic /Transport Issues & CTTP-2007 - 3 (Projected Mass Transport - Desirable.JPG) Naveen - 10-APR-2008This image was uploaded with the post Traffic /Transport Issues & CTTP-2007 - 3. |
Traffic /Transport Issues & CTTP-2007 - 3 (CTTP - No MRTS within SE CBD.JPG) Naveen - 10-APR-2008
|
Part II: Non-Motorised User Facilities Naveen - 10-APR-2008
Pedestrian Facilities
Excerpts from various sections of the CTTP report are as follows : 3.13.1.9: There is high pedestrian traffic in core area and some other areas in Bangalore. Footpath facilities are generally not adequate and their condition is deteriorating. Therefore up gradation of their facilities is very important. 5.5.8 (Preferred Strategy for Transport Development): Special facilities for pedestrians within the entire network specially in the core areas; Pedestrianization of selected shopping streets in side the core area going to be served by Underground sections of Metro; Provision of pedestrian sky walks, under passes, footpaths and other road furniture along the roads where necessary. 7.9: Recommends as many as 78 roads within ORR & 54 roads outside ORR for improvements & widening. 7.11.2.2 (Foot paths): Recommends a width of 2.0m for sidewalks for about 350 kms of city roads. |
Naveen - 10-APR-2008
Bus Rapid Transit System (BRTS)
Earlier (1999), a feasibility study for BRTS had identified a promising network of 20 corridors for bus routes comprising twin central rings intersected by 8 radial routes, with assistance from SIDA, Sweden. A pilot project of 12kms from Jayanagar to Shivajinagar with a combination of exclusive lanes with priority of passage at signals & construction of rapid transit lines was planned but never materialized & was abandoned without any attempt. There is no mention of this in the CTTP-2007 report, either. If this had commenced then, we might have seen it progress to some extent & at least, public opinion about the value of such quicker means of public travel would have been recognized. |