Just noticed the numbers for land acquisition in the Feb Newsletter.
UG NS Stretch - Proposed: 14, Possession Taken: 8, Demolished: 7
UG EW Stretch - Proposed: 129, Possession Taken:0 (!), Demolished: 0 (!).
SPOTLIGHT AGENCIES
Suggestions for Metro Feeder Bus routes Naveen - 11-DEC-2010
BMTC had earlier requested suggestions for feeder bus routes for Metro (Reach-1). The suggestions were mapped on google & passed on to them for review. See map below, zoom in for better view or click link and view in google maps
|
Land Acquisition for Metro UG Stretch - expect more delays? Ravi_D - 2-MAR-2010
Just noticed the numbers for land acquisition in the Feb Newsletter. UG NS Stretch - Proposed: 14, Possession Taken: 8, Demolished: 7 UG EW Stretch - Proposed: 129, Possession Taken:0 (!), Demolished: 0 (!). |
Metro underground stretch - delayed by 6 months s_yajaman - 16-SEP-2009
Read this today. http://www.deccanherald.com/content/25489/metro-underground-work-behind-schedule.html |
vinod_shankar - 14-SEP-2009
Piles being put in place at RV road
skeletal structures for the piles |
Namma metro phase-I ridership projection and train operation frequency vinod_shankar - 7-AUG-2009
some of projections made in DPR of namma metro phase-I for ridership and train capacity and operation frequency. All the data presented below is without taking into account the north and south extension done at a later stage.
|
vinod_shankar - 1-AUG-2009
Objective tracking of namma metro from the data accumulated from the newsletter given out by BMRCL from feb 2009 upto july 2009 for reach-1. This will clearly give us trends on the progress of namma metro. I intend to update this data as and when new data is available. Here are the graphs. |
Metro Phase 1 extension approved swamy - 2-FEB-2009
Noticed one Bangalore Metro news - phase one extension was approved. From Deccan Herald: |