Metro Underground - Who Is Gaining the Expertise?

pdk - 19-NOV-2011

Came across this report in DH:  Metro’s Phase-I unlikely to meet deadline.  From June 2012, to December 2013, to March 2014 and now December 2014, though Mr Sreehari admits anything before mid-2015 is a pipedream.

Namma Metro UG-1 getting delayed??

vinpraja - 7-JAN-2011

Is Namma Metro UG-1 between Swastik to K.R.Road getting delayed? I tend to feel so as BMRCL is yet to award contract (in bmrc.co.in no info is given). Do note Ug-1 is crucial to Reach 4 as reach 4 lacks depot as well as full completion of Phase-1....

Eager to know about  when UG-1 tender is getting awarded and work starting on it...

Underground Parking - whats the big deal?

srinidhi - 6-DEC-2010

 It has been in news since some time that BBMP is planning underground parking lots under playgrounds and other public amenities like parks etc..

more on this in this link..

http://www.deccanherald.com/content/72003/are-playgrounds-last-resort-construction.html

Walkability & electricity

idontspam - 26-MAR-2010

“Overhead electrical cabling is a hazard to human life and property and poses an obstacle to road widening.The danger is even greater during the rainy and windy seasons. Also, a lot of power is stolen by miscreants,”  - A Bangalorean is determined to convince the government to go in for underground electrical cabling in the city

 I think the KPTCL & Bescom need to take this up on priority. This is an investment worth making. I know the linemen will lose gimbla as it will become harder to enable people to steal electricity. More than road widening 90% of obstructions on sidewalks/footpaths are related to electrical poles and transformers.

Let us take this up with our new corporators who will be at work soon.

Land Acquisition for Metro UG Stretch - expect more delays?

Ravi_D - 2-MAR-2010

Just noticed the numbers for land acquisition in the Feb Newsletter

UG NS Stretch - Proposed: 14, Possession Taken: 8, Demolished: 7

UG EW Stretch - Proposed: 129, Possession Taken:0 (!), Demolished: 0 (!).

Metro underground stretch - delayed by 6 months

s_yajaman - 16-SEP-2009

Read this today.

http://www.deccanherald.com/content/25489/metro-underground-work-behind-schedule.html

Urban development, costs of Metro and Indian budget - a perspective

asj - 10-OCT-2008

In my arguments with regards BRTS, I often bring up the key but neglected and forgotten matter of cost-effectiveness of a given solution to our transportation problems. It should come as no surprise to most who are acquainted with my stance that I hate the idea of spending money without a clear crsip rationale and long term plan.  And the Metro falls under this category as far as I am concerned.

MMRDA officials have in the past replied in agreement to my suggestion that Mumbai Metro will not solve its problems at all. Given the fact that 10000 daily migrants to Mumbai will swell it to a city 30 million plus by 2030, it will be fair to say that whether Mumbai gets sea links or Metro rail, people will still be travelling in quasi or near stampede like situations and roads will always remain clogged.