Kalyananagar junction flyover

UPCOMING EVENTS

Kalyananagar junction flyover

Project number 13667
Opened by USN Admin
Opened On 2020-08-18 14:08:46 +0530
Operations View all project cases

Kalyananagar junction Flyover- details as on 30.12.2011 Sl.No. Items Project Details 1 Project Name Construction of flyover along ORR at Kalyananagar junction 2 Owner Name BANGALORE DEVELOPMENT AUTHORITY 3 Financing 50% BDA, 50% Loan from KUIDFC (Megacity revolving fund) 4 Architect/Consultant M/s. IIIE LIMITED and M/s. S.N. BOBE ASSOCIATES 5 Contractor M/s. N.C.C. LIMITED 6 Project start date 09/11/2009 7 Project duration 31/12/2012 8 Project cost Rs.37,64,93,309.00 9 Amount released till date Rs.31,63,79,862.00 10 Sub-contractor details (If any) 1) Bearing - M/s. SAN FIELD LIMITED 2) Expansion joint - M/s. KANTA ENTERPRISES 11 Percentage of work completion 84%

There are no project blogs yet!

There are no project tasks yet!

There are no project wikis yet!