Project number 13671
Opened by USN Admin
Opened On 2020-08-18 14:09:18 +0530
Operations View all project cases

Devarabeesanahalli Flyover- details as on 17.12.2011 Sl.No. Items Project Details 1 Project Name Construction of flyover along ORR at Mahadevapura junction 2 Owner Name BANGALORE DEVELOPMENT AUTHORITY 3 Financing KUIDFC 4 Architect/Consultant M/s. NAGESH CONSULTANTS 5 Contractor M/s. SIMPLEX INFRASTRUCTURE LIMITED 6 Project start date 01/03/2010 7 Project duration 15 months 8 Project cost Rs.38.67 Crores 9 Amount released till date Rs.19.33 Crores 10 Sub-contractor details (If any) Nil 11 Percentage of work completion 86%

There are no project blogs yet!

There are no project tasks yet!

There are no project wikis yet!