4. THE PROPOSED TRAFFIC AND TRANSPORTATION PLAN
4.1 On the basis of projected traffic, an integrated multi-modal mass transport system plan on various corridors has been suggested in order to cater to traffic up to the year 2025. The mass transport systems have been proposed on various corridors considering expected traffic demand by 2025, available road right-ofways and system capacity. The balance traffic should be carried by road system in order to satisfy the needs of normal bus system and other modes such as two wheelers, cars, bicycles, trucks, pedestrians etc. The proposed Traffic and Transportation Plan for Bangalore contains the following types of proposals, which will cater to requirements of the projected travel demand up to the year 2025.
*Mass Transport System
-- Metro System
-- Monorail/LRT System
-- Bus Rapid Transport (BRT) System
-- Commuter Rail Services
*City Bus System
-- Augmentation of Bus Fleet
-- Grid Routes
-- Bus Terminal cum Traffic & Transit Management Centres (TTMC)
-- Volvo Depot cum Traffic & Transit centre
-- New Bus Stations/bus shelters
-- Additional Depots
-- IT Infrastructure
-- HRD Infrastructure
-- Environment Protection Projects
*Inter-city Bus Terminals
*Transport Integration
*Transport System Management Measures
*Pedestrian/NMT Facilities
-- Footpaths
-- Skywalks/Subways
-- Pedestrian zones
-- Cycle Tracks
*Road Development Plan
-- New Roads/Missing Links (Peripheral Ring Road, Core Ring Road, New Airport Expressway etc).
-- Road Widenings
-- Grade Separators
-- Re-alignment of Outer Ring Road
*Parking Facilities
*Integrated Freight Complexes
4.2 Integrated multi modal transport system has been recommended in order to ensure seamless travel. For the balance travel demand, road improvement proposals have been formulated. While making road proposals, entire corridor has been proposed to be improved instead of isolated improvements.
4.3 The proposed mass transport corridors are shown in Table 1 and Figure 1. Proposals pertaining to city bus system (other than BRT), parking, pedestrian and road improvement proposals are shown in Figures 2 -4 (below). Summary of proposals is given in Table 2.
4.4 Summary of the cost estimates for various projects is also given in Table 2. Overall cost of the entire plan is estimated as Rs 44,029 crore of which Rs 25,872 crore is proposed for Phase I (2007-12). Cost of the projects proposed in Phase II (2013-18) is Rs 17,017 crore.
Login or Register to post comments
PRAJA.IN COMMENT GUIDELINES
Posting Guidelines apply for comments as well. No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!